NRC still unclear why inspectors missed 'flaw' spot at Harris N - WSLS 10 NBC in Roanoke/Lynchburg Va

NRC still unclear why inspectors missed 'flaw' spot at Harris Nuclear Plant

Posted: Updated:
Harris Nuclear Plant will undergo more frequent inspections, federal regulators said Thursday night in Holly Springs. Harris Nuclear Plant will undergo more frequent inspections, federal regulators said Thursday night in Holly Springs.
HOLLY SPRINGS, N.C. -

An outside contractor hired to look for flaws in a Duke Energy nuclear reactor near Raleigh last year missed a quarter-inch spot of corrosion and cracking near the reactor core that forced a full shutdown last month after new eyes reviewing year-old data found the problem, federal regulators said Thursday.

Four smaller spots were fixed during a refueling last year, but the flaw that forced the May 15 shutdown at the Shearon Harris nuclear plant wasn't found until new contractors reviewed ultrasonic tests from last year, Nuclear Regulatory Commission inspectors said during a public meeting.

The NRC said there was never radiation leakage from the reactor vessel, which contains the heat and pressure produced by the nuclear core's energy. The plant returned to full power Sunday.

"The reason why they shut down was because they could not confirm that there was no leakage," said Robert Williams, an NRC reactor inspector who led a team looking into why the flaw was missed last year. "Once they shut down and were able to perform the needed and required examinations, they were able to confirm there was no leakage."

Had there been a leak from the reactor vessel as a result of such cracking, it would have been contained by backup safety systems, the NRC said.

Inspectors said they're still trying to figure out why a pair of expert-level outside analysts independently failed to spot the problem, and why the spot wasn't caught by later reviews of the data last year. A final NRC inspection report will be released by July 11.

Duke Energy "is taking actions to correct the failure of the personnel to identify the defect," the NRC said in a summary distributed at the meeting.

The cap on top of the reactor vessel, called a vessel head, will now be checked for similar cracks every time the reactor is refueled, NRC inspectors said. That's done every 18 to 24 months, the company said.

"They're looking at it every single time," Williams said.

About a third of all U.S. pressurized water reactors like Harris have similarly had cracking show up on a nozzle in the vessel head, the NRC said. The cracks are caused by the extreme temperatures of the water heated by the nuclear reaction and acid that results from boron mixed with the water to extend the life of the fuel, said Joe Austin, the senior NRC inspector stationed at the Harris plant.

Duke Energy took over the Harris plant after it acquired Raleigh-based Progress Energy Inc. last year, which made it the country's largest electric company. Duke Energy's two resulting operating subsidiaries in the Carolinas each have territories that serve parts of North Carolina and South Carolina that depend heavily on nuclear energy.

RELATED STORIES

RELATED LINKS

 

  • Former Va. governor's corruption trial begins

    Former Va. governor's corruption trial begins

    Jury selection is on the agenda for opening day in the corruption trial of a former Virginia governor and his wife in Richmond.
    Jury selection is on the agenda for opening day in the corruption trial of a former Virginia governor and his wife in Richmond.
  • Study: 35 percent in US facing debt collectors

    Study: 35 percent in US facing debt collectors

    Tuesday, July 29 2014 1:25 AM EDT2014-07-29 05:25:07 GMT
    More than 35 percent of Americans have debts and unpaid bills that have been reported to collection agencies, according to a study released Tuesday by the Urban Institute.
    More than 35 percent of Americans have debts and unpaid bills that have been reported to collection agencies, according to a study released Tuesday by the Urban Institute.
  • Be ready for 'prolonged' Gaza war, Netanyahu says

    Be ready for 'prolonged' Gaza war, Netanyahu says

    Monday, July 28 2014 10:26 PM EDT2014-07-29 02:26:43 GMT
    Israel and Hamas have lowered the pace of the fighting in the three-week-old Gaza war as international efforts intensify to end the conflict that has already killed 1,030 Palestinians and 43 Israeli soldiers.
    Signaling an escalation of Israel's Gaza operation, Prime Minister Benjamin Netanyahu told Israelis Monday to be ready for a "prolonged" war, and the military warned Palestinians in three large neighborhoods to leave...
Powered by WorldNow

WSLS 10, P.O. Box 10
Roanoke, VA 24022-0010

Telephone: 540.981.9110
Fax: 540.343.3157
Email: news@wsls.com

Can't find something?
Powered by WorldNow
All content © Copyright 2000 - 2014 Media General Communications Holdings, LLC. A Media General Company.